Johannesburg Metro Confirms Lilian Ngoyi Street Project 22% Complete After Delays

  The Johannesburg metro has confirmed that the Lilian Ngoyi Street rehabilitation project in the CBD is 22-percent complete - a year after a devastating explosion. Mayoral committee member for Transport, Kenny Kunene, says the project has stalled, with dire consequences for road users, businesses and residents. So far, more than 17-million-rand has been spent out of the total of almost 180-million-rand allocated for the project's completion. Kunene told SABC […]

todayNovember 12, 2024 21